Process and Timeline

Once your application is submitted, this chart indicates approximately how much time is involved in each step in the process of becoming a franchising owner.

  1. Initial Screening and Franchise Applications: 1 - 2 weeks
  2. Complete Financial Qualifications: 1 - 2 weeks
  3. Franchise Development and Operations Interview: 3 weeks
  4. Franchise Agreement and Approval: 3 weeks
  5. Site Submitted: 12 - 24 weeks
  6. Real Estate and Construction Process: 16 - 26 weeks
  7. Green Beans Worldcafé Opening: 2 weeks